Construction Oversight Form - Exhibit L

View the Construction Oversight Form for the Final Completion Certificate. “Final Completion” means the date upon which the Work is complete in accordance with the terms and conditions of the Contract, including punch list items. The date of Final Completion shall be set by the Agency as a certain number of days after Substantial Completion. Any additional or supplemental Work after this date due to Construction Contractor error or omission shall be completed by the Construction
Contractor without additional compensation.

Construction Oversight Form - Exhibit K

View the Construction Oversight Form for the Substantial Completion Certificate. "Substantial Completion” means the date determined and certified by the Design Professional’s and/or Agency Designated Representative’s signature, when the Work, or a designated portion thereof, is sufficiently complete in accordance with the Contract, so as to be operational, fit for the use intended, and so the Agency may occupy the Work.